Compare Colocation Providers: Buyer Scorecard and Checklist

Reviewed October 21, 2026 · Godatacenters buyer tools

Compare colocation providers against the same deployment brief: available IT power, delivery date, rack density, cooling, resilience, connectivity and total commercial cost. A facility belongs on your shortlist only when it can meet your essential requirements. Missing evidence is an open question, not a pass.

Free buyer scorecard: Download the two-page comparison worksheet and deployment brief (PDF). No signup required. Use one copy per facility and bring the unresolved questions to your next provider discussion.

Start with the workload and the date

Before comparing buildings, write down your initial IT load, expansion load, average and peak rack density, hardware model, cooling requirements, target markets, network needs and required service date. Identify which requirements are essential and which can change. A lower price does not resolve a mismatch in cooling or delivery timing.

Ask providers to respond for the exact building, hall or suite proposed for your deployment. Separate operating infrastructure from work still awaiting engineering, equipment, permits, utility delivery or commissioning. Record the evidence date and any conditions alongside the answer.

Use the same seven questions for every provider

Decision factorWhat to requestWhat keeps the decision open
1. Power and deliveryIT capacity available to your deployment, the proposed start date and the dependencies behind it.A campus total or a future expansion figure without an allocation and delivery plan.
2. Density and coolingAverage and peak rack kW, supported equipment, cooling interfaces and the scope of any required retrofit.An “AI-ready” label without evidence for your hardware and deployment area.
3. ResiliencePower and cooling paths, maintenance procedures, failure scenarios and the exact scope of any Tier award.A redundancy label without an explanation of how the proposed space operates during maintenance or failure.
4. ConnectivityCarriers and cloud services at the building, physical route diversity, installation dates and cross-connect charges.A carrier list without confirmation of the service and route your workload requires.
5. Operations and assuranceAccess controls, remote-hands scope, escalation procedures and relevant audit scope and reporting period.A logo or certificate that does not cover the contracting entity, service or location.
6. Commercial termsRecurring and one-time charges, energy billing, ramp, escalation, deposits, renewal and exit provisions.Quotes built around different power, term or service assumptions.
7. ExpansionThe next capacity block, reservation terms, target dates and engineering dependencies.An expansion roadmap without clear rights, timing and delivery responsibilities.

Mark each row Pass, Hold or Fail. Define a pass against your own requirement. Keep a hold until the missing evidence arrives. Do not let a combined score conceal a failed essential requirement. Once the candidates meet those requirements, compare the remaining trade-offs using weights agreed by your engineering and procurement teams.

Read power and cooling claims in context

Ask what a power figure measures: utility supply, backup generation, installed IT capacity, planned capacity or capacity currently available for a customer. Record the unit, building or campus scope, source and date. These figures answer different questions and should not be substituted for one another.

Use the equipment manufacturer’s requirements for your actual hardware configuration. Confirm electrical connections, rack weight, airflow or liquid interfaces, heat rejection and maintenance access. NVIDIA publishes system-specific installation and operating documentation; a general GPU or AI label cannot replace that specification. Reference: NVIDIA DGX system documentation.

Power usage effectiveness, or PUE, compares total facility energy with IT equipment energy. When a provider quotes it, ask about the measurement boundary, period and load conditions, and how it affects your bill. A PUE figure alone does not establish cooling compatibility or the total price of your deployment. Reference: The Green Grid PUE overview.

Verify resilience and assurance claims

Request the proposed power and cooling topology and ask what happens during maintenance and equipment failure. Component redundancy, distribution paths and operating procedures need to be considered together. Avoid treating a generator count or an N+1 label as a complete description of resilience.

If a provider claims Uptime Institute certification, verify the specific facility and award. Design-document certification, constructed-facility certification and operational assessments have different scopes. Uptime Institute describes Tier III as concurrently maintainable and Tier IV as fault tolerant; confirm the actual award rather than treating marketing wording as certification. Reference: Uptime Institute Tier certification.

For security and assurance, ask your internal owners to identify the controls and evidence the workload needs. Review the entity, location, services, exclusions and period covered by each report. Confirm which responsibilities remain with your organization. A facility’s assurance documents do not automatically cover every customer application.

Compare the full commercial scope

Ask every candidate to price the same IT load, ramp, contract length, energy assumptions and services. List recurring capacity charges, metered energy or pass-throughs, cooling charges where applicable, cross-connects, remote hands, installation and fit-out separately. Keep refundable deposits separate from expenses.

Model an expected-use case and a slower ramp. Record which charges begin on the service date, which begin when equipment arrives and which apply even if capacity is unused. Ask your commercial advisers to review escalation, delay, renewal, termination and service-credit provisions against the actual proposal.

Use the existing pricing guide for additional context and the powered-shell versus turnkey guide when deciding who will deliver the infrastructure. Published benchmarks are not a live quote for a particular site.

Turn the answers into a shortlist

  1. Explore the Godatacenters directory by location and reported power.
  2. Save candidates and use the shortlist to compare published information.
  3. Complete the buyer scorecard, keeping unconfirmed answers visible.
  4. Share your requirements for follow-up on suitable options.

Directory presence and reported power do not establish current availability. Confirm the proposed space, specifications and commercial terms during sourcing. You approve provider introductions before contact details are shared.

Common buyer questions

Can I compare providers using dollars per kW alone?

Only after aligning the billing basis, term, ramp, included services and other charges. Compare the complete proposal over the same period; a headline rate can leave out material items.

Does a data center’s published MW figure mean I can lease it?

No. Establish what the figure describes, then ask how much IT capacity can be allocated to your deployment and on what date.

Does every AI deployment need the same cooling?

No. Start with the specifications for your actual equipment and layout. Confirm support in the proposed deployment area, including any upgrades still required.

Where can I keep up with the buying questions that matter?

Follow Godatacenters on LinkedIn for practical guidance on power, cooling, delivery dates and colocation decisions.

← All insightsBack to top ↑

Keep exploring

All insights →

FROM RESEARCH TO REQUIREMENTS

Your next location starts here.

Search the global directory by location and power, or build a brief with our concierge team.

Search sites ↗Build your brief →